The sole shareholder of West Properties, Donal Mulryan said work on Origin had been halted while the interior design of the anchor component, the W Hotel, was finalised, and he expected work to begin again within four to five months.
"It is about 12 months behind schedule, but both sides are committed to the project and we feel 2011 is a good year to be opening a hotel in Manchester," said Mr Mulryan.
"Getting the W hotel was a coup, and it is a very, very viable product for the site.
This is an extract from a recent article in the Manchester Evening News dated 10th May 2009.
I had spoken to a director at West on 31st March 2009 and was told completion was on track for September 2010 and that work on the site would recommence in two months.